1- Design and Supervision of Construction of Wastewater Projects in the Central Region of Lebanon
1998 - 2001
NAME OF CLIENT: Council for Development and Reconstruction, Lebanon
VALUE OF CONSTRUCTION Million US $: 6

This project consists of the design and site supervision of construction of sewers networks and house connections for the towns of Aley Barouk - Fraidis, Bhamdoun el Mahata and Deir El Kamar in Lebanon. This multi-million dollar sewer project for the Council for Development and Reconstruction in Lebanon included over 40 kms of sewer pipes ranging in diameter from 150mm to 500mm. The work included developing and Tender Documents as well as the site supervision of construction of the works.

Top
2- DESIGN AND PREPARATION OF TENDER DOCUMENTS FOR JERICHO WASTEWATER SYSTEM AND TREATMENT PLANT AND EFFLUENT REUSE. - JERICHO - 1998
1998 - 2000
NAME OF CLIENT: Palestine Economic Council for Development and Reconstruction (PECDAR).
VALUE OF CONSTRUCTION Million US $: 10

Prepared an environmental assessment report, detail design and preparation of tender documents, study the effluent reuse for agricultural purpose and prepare detailed cost analysis for the works. Regarding the Design of Wastewater Treatment Plant and Effluent Reuse, the works include search for a land suitable for STP, study wastewater characteristics, perform topographic survey and geotechnical investigations study and make preliminary design of a minimum of 4 different treatment options, the works also include the preparation of institutional arrangements to manage the treatment facilities, collection system and effluent reuse, and the preparation of operation and maintenance manual.
An environmental assessment study was carried out for the impact of the present situation on the environment and the impact of the various treatment options thus proposing the best treatment and effluent to be reused for agricultural purposes.

Top
3- Economic Feasibility Study, Preliminary and Final Design of Sewerage, Drainage and Water Supply Systems in Eight Palestinian Refugee Camps in Lebanon - Lebanon - 1997
1997 - 2000
NAME OF CLIENT: United Nations Relief and Works Agency
VALUE OF CONSTRUCTION Million US $: N/A

The design of Sewerage, Stormwater Drainage and Water Supply networks for Eight Palestinian Refugee Camps in Lebanon. It involves the design of over 40 kms of sewer pipes, 40 kms of water mains and 11 kms of stormwater drainage pipes, 13 water supply bore holes, 7 elevated water reservoirs, 2 sewage pump stations and for a total area of 164 hectares. The work involved includes developing conceptual studies, preparing economic feasibility studies and reports, preparing environmental impact assessments and preparing preliminary and final design and drawings and tender documents for the eight camps.

Top
4- Sewerage Collection Systems for the Central Regions of Barouk - Fraidis, Deir El Kamar in Caza Chouf and West of Aaley, Bhamdoun El Mhatta in Caza Aaley - in Lebanon
1997 - 2000
NAME OF CLIENT: Council for Development and Reconstruction C.D.R
VALUE OF CONSTRUCTION Million US $: 9

Design report, final design, tender documents and supervision of construction for sewage collection systems for the town of Barouk - Fraidis, Deir El Kamar, West of Aaley and Bhamdoun El Mhatta, about 41.5 kms of sewer lines and preliminary design for wastewater treatment plant for the town of Barouk – Fraidis

Top
5- Sewerage Collection Systems for the Central Regions of Barouk - Fraidis, Deir El Kamar in Caza Chouf and West of Aaley, Bhamdoun El Mhatta in Caza Aaley - Lebanon
1997 - 1999
NAME OF CLIENT: Council for Development and Reconstruction C.D.R
VALUE OF CONSTRUCTION Million US $: 9

Design report, final design, tender documents and supervision of construction for sewage collection systems for the town of Barouk - Fraidis, Deir El Kamar, West of Aaley and Bhamdoun El Mhatta, about 41.5 kms of sewer lines and preliminary design for wastewater treatment plant for the town of Barouk – Fraidis

Top
6- Sewage Collection Systems for Towns of Tulkarem (Irtah and Dhannaba Areas) and Jenin (four different locations) in West Bank.
1996 - 1998
NAME OF CLIENT: Palestine Economic Council for Development and Reconstruction (PECDAR).
VALUE OF CONSTRUCTION Million US $: 2

Design Report, final design and specifications and tender documents for sewage collection system in the Towns of Tulkarem (about 14 kms) and Jenin (about 12 kms).

Top
7- WASTEWATER SYSTEM AND WASTEWATER TREATMENT PLANT FOR LEBOUE - Lebanon
1996 - 1998
NAME OF CLIENT: Council for Development and Reconstruction
VALUE OF CONSTRUCTION Million US $: 12
The project consists of a Preliminary Study, Final Design, and Supervision of construction works for a complete system including wastewater network, a collector wastewater line and a wastewater treatment plant.

The wastewater treatment plant consists of screening, oxidation ditches, clarifiers, screw lift pumps, lift station and sludge drying beds. It provides a secondary level treatment and it is designed to accommodate an average daily flow of 5,250 cubic meters, which shall serve the towns of Laboue, Nabi Osman and El Ain for a design period of 25 years.
Top
8- Master Plan and Feasibility for Rehabilitation, Expansion and Development of Existing Wastewater Systems in Amman - Zarqa River Basin Area
1995 - 1997
NAME OF CLIENT: USAID for the Ministry of Water and Irrigation
VALUE OF CONSTRUCTION Million US $: N/A
The project addresses the planning, analysis and preliminary design of components of the waste water collection, treatment and reuse system in Amman - Zarqa River Basin through year 2025.
The project goal is to provide wastewater collection, treatment, and reuse for customers who is reliable, efficient, cost-effective, environmentally sound, and financially sustainable.
Top
9- Master Plan and Feasibility for Rehabilitation, Expansion and Development of Existing Wastewater Systems in Amman - Zarqa River Basin Area - Jordan
1995 - 1997
NAME OF CLIENT: USAID for the Ministry of Water and Irrigation
VALUE OF CONSTRUCTION Million US $: 2

The project addresses the planning, analysis and preliminary design of components of the waste water collection, treatment and reuse system in Amman - Zarqa River Basin through year 2025.
The project goal is to provide wastewater collection, treatment, and reuse for customers which is reliable, efficient, cost-effective, environmentally sound, and financially sustainable.

Top
10- Sewerage and Stormwater Systems for Towns of Anabta, Tulkarem and Qalqilia in West Bank.
1995 - 1997
NAME OF CLIENT: Palestine Economic Council for Development and Reconstruction (PECDAR).
VALUE OF CONSTRUCTION Million US $: 2.7
Design report, final design and specification and tender documents for the sewerage and stormwater systems in Towns of Anabta, Tulkarem and Qalqilia. The components of the systems included around 10.0 km of sewer lines and 5.6 km of stormwater drainage lines.